Gantt Chart doesn’t spread out in Project 200

P
Patrick Liu 👤 Member for 22 years 4 months
P
Patrick Liu 👤 Member for 22 years 4 months

My problem is solved already (and that’s exactly what’s causing the problem), thanks anyway.

M
MK TSE 👤 Member for 24 years 4 months

Check the setting for calculation in option. I think you have use manual type rather auto.

P
Patrick Liu 👤 Member for 22 years 4 months

Hi Jafar,

It’s Microsoft Project 2000 that I had this problem with.

J
Jafar Zarei 👤 Member for 22 years 11 months

Hi

would you please let me know which windows you are using?

kaid ragards

Jafar Zarei

P
Paul Harris 👤 Member for 25 years 2 months

You may have manual calculation set. Press the F9 key to calcualte the schedule.



This setting is set by selecting Tools, Options, Calculation.



This is a system setting and affects all schedules opened on the machine and is not saved as a project setting, so the schedule may calculate automatically on another machine.



Paul E Harris

Eastwood Harris Pty Ltd

Planning and Scheduling Book Publishers

www.eh.com.au

F
Forum Guest 👤 Member for 17 years 5 months

I have already set (or MS Project sets) the constraint type to "as soon as possible" when I started out the project. The problem is still there unfortunately. Any other ideas?

F
Forum Guest 👤 Member for 17 years 5 months

HI Patrick,



Try checking constraint type. It might be set to early constraints. Replace your constraint type to as sson as possible constraint.



Hope this would help.


Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts