Mechanical & Electrical commissioning
Forum Sponsor
Top Posters
Adrian Fletcher
12 posts
GeoVe
0 posts
James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Hi Neil
I can help with this as I carry out services planning and worked as a commissioning manager for several years.
It would be just great if we could start commissioning at the end of 1st fix but unfortunately this is not possible, and as Andrew says it depends on your planners definition and content of his 2nd fix activities.
I know it sounds obvious but what you are looking for is system completion. In your case I guess you will have at least 2 enclosed water systems (a heating system (LTHW) and a chilled water system (CHW)) and several ventilation systems. If you can work out when these systems will be complete (we are talking 100% here and nothing less!) then this will give you your commissioning start dates.
Mechanical system commissioning should start with a water systems as 9 times out of 10 these form part of the commissioning critical path. Aim to ensure that the larger of the 2 water systems is completed first as cleaning and balancing are directly related to the system size.
Electrical testing will need to start prior to your mechanical commissioning as power is required for this.
Get in touch if you want to discuss this further, Im sure I have got a commissioning flow chart somewhere which will help you, and I would be happy to help with advise on your programme.
Paul.
This is a common problem, unless you are a qualified M & E engineer it is difficult to actually define what commissioning means.
It can be broken down into stages
Testing of systems as work proceeds. - pressure tests etc
Static completion of plant and systems
Flushing & cleaning wet systems,
Blowing out and claening duct systems,
Setting to work plant
All of the above can be progressed as work nears completion
at end of/during 2nd fix (depending on the interpretation of 2nd fix)
Get your sun contractor to explain what they mean by commissioning and what constraints they put on your programme!
Final balancing of air and water systems needs each system to be balanced complete, windows and doors in place permenant power on etc.
use pre commissioning & testing
and after that use Commissioning & Testing
thanks
Iqbal