Moving tasks

A
Andy Rowe 👤 Member for 22 years 4 months
M
MK TSE 👤 Member for 24 years 4 months

Agree with Paul. Make sure "small group are connected with logic and do not have constraints" This is the key.

P
Paul Harris 👤 Member for 25 years 2 months

If all the tasks in the small group are connected with logic and do not have constraints (and depending on your constraints option in the options form) changing the early start constraint date on the first task should move all the tasks.



There are too many options in Microsoft Project and it is difficult to predict what will happen in other people’s projects.



I suggest you display the indicators column and this will show you which activities have constraints.



Other wise you may have manual recalculation switched on and have to hit the F9 key.



Paul E Harris

Eastwood Harris Pty Ltd

Planning and Scheduling Book Publishers

www.eh.com.au


F
Forum Guest 👤 Member for 17 years 5 months

Paul, many thanks for your response.



The tasks I want to move are a small group within a larger project. I have created links between them and constrained the first of them to start on a specific date. I still cant get them all to move as one....I need to mve them all by two weeks.



Hope that is clearer



Andy

P
Paul Harris 👤 Member for 25 years 2 months

Andy



People usually have tasks in Microsoft Project linked with relationships whereby moving the first task will move all the successor tasks. I am unsure from the info you have provided how you have scheduled your tasks. There are several ways of delaying tasks by two weeks:



1. You may change the project start date and this will move any unstarted tasks that are scheduled on the start date to the new start date.



2. Typing a date in the Task Start column will assign an early start constraint to the task. If you have a number of tasks that you wish to start on the same day you may use the Fill Down or Copy and Paste function to assign a constraint to a number of activities.



3. If you do not have relationships between tasks, put some in and assign a constraint to the fist task.



Paul E Harris

Eastwood Harris Pty Ltd

Planning and Scheduling Book Publishers

www.eh.com.au

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts