I dont think what Faisal suggested exactly solve the issue.
The questioner want to prominently show the planned start and finish dates.
In your method, when ever we enter a date in the Actual start ,for all associated activities, Start And Finish date changes !
That means one wont be able to see the originally planned start and finished dates in the programme anymore! Duration variance will display some value only after we enter Actual start & actual finish (Both)
The best solution MSP can offer for this is:
Step-01: As soon as the project plan (Baseline) is approved , save it as baseline : Tools > Tracking > Save baseline > Entire project
Step-02: Right click on the Gantt chart area , select "Gantt Chart Wizard". In the wizard step02 , select Baseline view and proceed for formatting.
Now what ever you do with start & finish dates / links , your original plan lays undisturbed in the backdrop as Baseline So anytime you can have a visual comparison of what was planned and what happened in real.
You may change the colour of baseline plan to some thing contrasting from the "actual" bar colour (In bar styles)
go to insert/column/select the ID "actual start" and "actual finsih". two new columns will be inserted u can now feed in yor actual start and actual finish dates in these columns feeding these will also give you the days variance by again going the insert / column and selecting the ID Duration variance. this is how it is
You are doing a big mistake: in MSP vocabulary, "Duration", "Start" and "Finish" are equivalent to "Original Duration", "Early Start" and "Early Finish" in P3; you should add "Scheduled" to the noun, to make the difference from Baseline and Actual.
Furthermore, when you enter actuals in MSP, the software supersedes the scheduled values with the actuals.
Therefore, a)when a task has started, "Start" is equal to "Actual start", b)when a task has finished, "Duration" is equal to "Actual Duration" and "Finish" to "Actual Finish"; no need to use Start1 and Finish1, use Baseline instead
Save as baseline is an option. But If you want to keep your current start & current finish unchanged after updating then copy all start & finish date in the field start1 & finish1. Then you can update the actual start & finish date.
You MUST enter the actual start end finish dates in the ACTUAL START / FINISH fields, not the (current) START / FINISH fields.
Before you entetr the 1st actual data, go to Tools, OPtions, Tracking and Save the baseline of your project.
ACTUAL dates will not modify / update the part of the planning already completed; if the actual does not comply with the planned, the still to be done part of the project will be updated.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
I didnt meant that adding two new columns of actual start and actual finish will not change the original duration try doing it it wont change it
Hi!
I dont think what Faisal suggested exactly solve the issue.
The questioner want to prominently show the planned start and finish dates.
In your method, when ever we enter a date in the Actual start ,for all associated activities, Start And Finish date changes !
That means one wont be able to see the originally planned start and finished dates in the programme anymore! Duration variance will display some value only after we enter Actual start & actual finish (Both)
The best solution MSP can offer for this is:
Step-01: As soon as the project plan (Baseline) is approved , save it as baseline : Tools > Tracking > Save baseline > Entire project
Step-02: Right click on the Gantt chart area , select "Gantt Chart Wizard". In the wizard step02 , select Baseline view and proceed for formatting.
Step-03: Add two more columns :Insert > Columns
"Baseline Start" & "Baseline Finish"
Step-04 : Periodically update "Start" & "Finish| columns.
Change activity links as Performed
Now what ever you do with start & finish dates / links , your original plan lays undisturbed in the backdrop as Baseline So anytime you can have a visual comparison of what was planned and what happened in real.
You may change the colour of baseline plan to some thing contrasting from the "actual" bar colour (In bar styles)
Hope this helps ..
Cheers
Sreejith Nair
there is a simple answer to this simple question
go to insert/column/select the ID "actual start" and "actual finsih". two new columns will be inserted u can now feed in yor actual start and actual finish dates in these columns feeding these will also give you the days variance by again going the insert / column and selecting the ID Duration variance. this is how it is
Nicolas,
You are doing a big mistake: in MSP vocabulary, "Duration", "Start" and "Finish" are equivalent to "Original Duration", "Early Start" and "Early Finish" in P3; you should add "Scheduled" to the noun, to make the difference from Baseline and Actual.
Furthermore, when you enter actuals in MSP, the software supersedes the scheduled values with the actuals.
Therefore, a)when a task has started, "Start" is equal to "Actual start", b)when a task has finished, "Duration" is equal to "Actual Duration" and "Finish" to "Actual Finish"; no need to use Start1 and Finish1, use Baseline instead
Gentlemen,
Searching for exactly the solution to this problem,
I came upon this thread.
It shows the search engine is accurate but,
when I tried to implement Rajs solution,
I found that updating actual start still
moves the "current" start.
Of course I could modify the bars to show
Start1 and End1 instead of Start and End
but this would be a pain
Any suggestions
Thanks in advance.
Save as baseline is an option. But If you want to keep your current start & current finish unchanged after updating then copy all start & finish date in the field start1 & finish1. Then you can update the actual start & finish date.
Hello,
You MUST enter the actual start end finish dates in the ACTUAL START / FINISH fields, not the (current) START / FINISH fields.
Before you entetr the 1st actual data, go to Tools, OPtions, Tracking and Save the baseline of your project.
ACTUAL dates will not modify / update the part of the planning already completed; if the actual does not comply with the planned, the still to be done part of the project will be updated.
Alexandre Faulx-Briole