Provisional Sum v/s Variation Order
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Pradeep !
You are absolutely right.
You have to substantiate with invoices/vouchers etc added up with your OH&P.
Cheers
Thanx Jogi...
If we read clause 58.2, the PS is instructed by engineer to contractor (a), AND nominated sub contractor (b).
That means...the contractor will coordinate the works ONLY and will be paid as per 59.4. FIDIC doesnt mention that PS has to be carried out by contractor ALONE.
So the engineer cannot instruct the contractor to do PS based on BOQ rates and hence a separate nominated sub contractor has to be appointed where the contractor takes his overheads and profit.
Am I right on these lines??
Hi
Pradeep !
Contractor can not object to carry out works which are:
expressly required to complete the said project
affected by price escalation,unless Clause related to "Changes in Cost and Legislation" exists in Contract.
Hope,you got it.
Cheers