Are you sure that P3 does not have zero free float constraint? I am sure it had it last time I looked.
Anyway, that is not relevant to this problem.
You could use a spare flag field to mark the Tasks you want to show at the late dates. Then make a new View (copy the Gantt Chart View). Then make a Bar Style which draws a bar from Late Start to Late Finish using "Task, Flag*" as the criteria. I would use a different colour so you can see the late flagged Tasks. This would just be a variation on the built in Detail Gantt View.
P3e does not have the zero float constraint that I remember from P3, only ALAP, which uses up the free float but not the total float. I suspect from my experience and your answer plus other inputs that this simply doesnt exist in MSP. ALAP uses up the total float on an activity - as you say not v. useful!
By the way, do you or anyone else know if there is a term for the start and finish dates at the back end of free float (in the sense of early and late dates, where late dates are at the back end of total float)?
P3 has a zero total float constraint. Useful. MSP does not.
Does P3s ALAP slide the Task to the end of FRee Float? MSPs ALAP is very strong. If applied to a noncritical Task it sucks all of the Float out of the Successors as well. Not v useful.
I have a test set up where this seems to be working only partially:
A 1 day task showing 3 days Free Slack gives a start date 2 days after Early Start using the formula ProjDateAdd([Early Start];[Free Slack];[Project Calendar]). The same formula with Early Finish gives a finish date 3 days after Early Finish. Any ideas why this could be?
Another question: Does anyone know how to make the task itself move to the end of its Free Slack? (In other words the same action as the "As late as possible" constraint in Primavera)
Certain fields (Task: Cost1-10, Date1-10, Duration1-10, Finish1-10, Flag1-20, Number1-20, Start1-10, Text1-30; Resource: same as for Task) can have formulas.
Display the column, RightMouseButton on the column title and pick Customize fields from the popup menu.
To put in a formula, click on the Formula button.
Theres a number of Help topics associated with Formulas. Try a few things, if you have problems, report back with the formula thats giving you issues.
if I understood it correctly the question was about showing not Late Dates defined by Total Float but Late Dates defined by Free Float. I dont understand your solution of this task, please explain in more details.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
P3 does have a Zero Free Float but P3e does not.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
Are you sure that P3 does not have zero free float constraint? I am sure it had it last time I looked.
Anyway, that is not relevant to this problem.
You could use a spare flag field to mark the Tasks you want to show at the late dates. Then make a new View (copy the Gantt Chart View). Then make a Bar Style which draws a bar from Late Start to Late Finish using "Task, Flag*" as the criteria. I would use a different colour so you can see the late flagged Tasks. This would just be a variation on the built in Detail Gantt View.
Hi Trevor
P3e does not have the zero float constraint that I remember from P3, only ALAP, which uses up the free float but not the total float. I suspect from my experience and your answer plus other inputs that this simply doesnt exist in MSP. ALAP uses up the total float on an activity - as you say not v. useful!
By the way, do you or anyone else know if there is a term for the start and finish dates at the back end of free float (in the sense of early and late dates, where late dates are at the back end of total float)?
Jerry
P3 has a zero total float constraint. Useful. MSP does not.
Does P3s ALAP slide the Task to the end of FRee Float? MSPs ALAP is very strong. If applied to a noncritical Task it sucks all of the Float out of the Successors as well. Not v useful.
I have a test set up where this seems to be working only partially:
A 1 day task showing 3 days Free Slack gives a start date 2 days after Early Start using the formula ProjDateAdd([Early Start];[Free Slack];[Project Calendar]). The same formula with Early Finish gives a finish date 3 days after Early Finish. Any ideas why this could be?
Another question: Does anyone know how to make the task itself move to the end of its Free Slack? (In other words the same action as the "As late as possible" constraint in Primavera)
Jerry Clarke
Works perfectly !
(Customize in French is Personnaliser)
Thanks again!
Nicolas
Thanks a lot L.E.N.
I shall try it and let you know
maybe with some more questions
regards
Starting with P2000 ...
Certain fields (Task: Cost1-10, Date1-10, Duration1-10, Finish1-10, Flag1-20, Number1-20, Start1-10, Text1-30; Resource: same as for Task) can have formulas.
Display the column, RightMouseButton on the column title and pick Customize fields from the popup menu.
To put in a formula, click on the Formula button.
Theres a number of Help topics associated with Formulas. Try a few things, if you have problems, report back with the formula thats giving you issues.
Hi all,
Alexandre,
I am totally new to theses formulas you guys talk about.
Could you explain a little and maybe
write a few words of "how-to"
for us newbies, pls?
thanks a lot in advance
Hi
Thanks again for the tips. The formula required is the following:
ProjDateAdd([Early Start];[Free Slack];[Project Calendar])
Works well especially for; awarding sub contractors and site mobilsation.
Cheers
Craig
Thanks for your help. Ill give it a try and let you know how I got on.
Thanks
OK,
I missed the point
the formula is (in French): ProjDateSub([Fin repoussée au plus tard le];[Marge libre];[Calendrier du projet]); should be in English:
ProjDateSub([Latest Finish Date];[Free Slack];[Project Calendar]), or something close
Hope this help this time
Alexandre
Alexandre,
if I understood it correctly the question was about showing not Late Dates defined by Total Float but Late Dates defined by Free Float. I dont understand your solution of this task, please explain in more details.
Regards,
Vladimir
Hi,
Create a formula such as Flag1 = Yes if Free Float > 0
Create a bar style that associates the said formula, then display the late start date along with the bar
There you are
Alexandre