Status Date and Work Shown to be Perfromed Before

A
Alexandre Faulx-Briole 👤 Member for 23 years 5 months

Hello,

go to Tools, OPtions, Calculation, use the options #2 to #5 under Calculation options for (current) project (don’t know the exact name in English as I am using the French version)

looks like MS Project would like to simulate P3, with limited success

Alexandre

A
Andrew Owenson 👤 Member for 20 years 7 months

N



Cannot help with the how, but if you go to Tools, Tracking, Update Project. Tick the reschedule uncompleted work, as long as your status date is correct the activities will adjust to the right of the status date - works for me



Best Regards



Andrew