Thanks for replying, the bar is not a summary bar its a normal activity bar. my main point being is that I have done a third of the duration in the first week, but the progress shows a third done but over the whole original period, which makes the end date for that activity wrong. The progress line is showing that the activity is ahead of programme % wise but finishes late due to the late start.
The % Complete of duration is actually a bit funny in the way it calculates it at summary level. However, in essence, it looks at the durations of each individual activity and calculates the summary based on the sum total of those durations.
Example: two activities. A1=20 days, A2=10 days. Total activity days = 20+10=30 days. If A1=20% complete (4 days) and A2=80% complete (8 days), the summary % Complete will be [4+8]/30= 40% Complete. It DOES NOT look at the duration of the summary bar itself.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Nicolas,
A)please check your calender day.. did you put any holiday ?
B) go tool > option > calculation ... check all the command.
Hi Andrew
Didnt you check the
"fixed duration" on that task? ({Shift}{F2})
In that case it seems normal that the duration
does not change?
hth
Nicolas
James
Thanks for replying, the bar is not a summary bar its a normal activity bar. my main point being is that I have done a third of the duration in the first week, but the progress shows a third done but over the whole original period, which makes the end date for that activity wrong. The progress line is showing that the activity is ahead of programme % wise but finishes late due to the late start.
Best Regards
Andrew
Hi Andrew,
The % Complete of duration is actually a bit funny in the way it calculates it at summary level. However, in essence, it looks at the durations of each individual activity and calculates the summary based on the sum total of those durations.
Example: two activities. A1=20 days, A2=10 days. Total activity days = 20+10=30 days. If A1=20% complete (4 days) and A2=80% complete (8 days), the summary % Complete will be [4+8]/30= 40% Complete. It DOES NOT look at the duration of the summary bar itself.
HTH
James.