Graphical Indicators for Variances (Custom Task Field)

B
Brian Ultican 👤 Member for 19 years 1 month

First off there is an error in your formula so that it counts weekends into the number of days. Because of this a task that is only really only 19 working days late is shown by your formula to be 27 days late. I have made some adjustments below:

IIf([% Complete]=100,"Task completed",IIf(ProjDateConv([Baseline Finish])="NA","Task not agreed",IIf((ProjDateDiff([Baseline Finish],[Finish],"Standard")/60/8)<=20 And (ProjDateDiff([Baseline Finish],[Finish],"Standard")/60/8)>7,"Task >1 week late",IIf((ProjDateDiff([Baseline Finish],[Finish],"Standard")/60/8)>20,"Task >4 weeks late","Task on schedule"))))



As for your issue I cannot reproduce it. I get indicators as expected for all values.

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts