Graphical Indicators for Variances (Custom Task Field)

B
Brian Ultican 👤 Member for 19 years

First off there is an error in your formula so that it counts weekends into the number of days. Because of this a task that is only really only 19 working days late is shown by your formula to be 27 days late. I have made some adjustments below:

IIf([% Complete]=100,"Task completed",IIf(ProjDateConv([Baseline Finish])="NA","Task not agreed",IIf((ProjDateDiff([Baseline Finish],[Finish],"Standard")/60/8)<=20 And (ProjDateDiff([Baseline Finish],[Finish],"Standard")/60/8)>7,"Task >1 week late",IIf((ProjDateDiff([Baseline Finish],[Finish],"Standard")/60/8)>20,"Task >4 weeks late","Task on schedule"))))



As for your issue I cannot reproduce it. I get indicators as expected for all values.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts