Resource Units & Leveling

M
mimoune djouallah 👤 Member for 19 years 8 months

hi



"In addition, it can also drive the physical % complete base on actual hrs. Non labor unit is not counted when use EVMS"



is there any clause, reference of evms that say that explicitly.



thanks very much.



mimoune

A
Alex Wong 👤 Member for 23 years 4 months

minhas



first part of your question. Labor / non labor unit



Labor unit is use in the EVMS calculation for CPI/SPI (Hr)

In addition, it can also drive the physical % complete base on actual hrs. Non labor unit is not counted when use EVMS.



Secondly, to level 5000hrs/week as your top usuage level.

2 ways you can achieve this

1. Firstly you determinate what exactly the trade personnel splite (ie 2000 hrs electrician 1000 hrs labor 500 hrs supervisor ...) then you level all the selected resource and view the resource usage to see whether it exceeds its 5000 hrs limited.



2. Create a dummy resource call "labor" set the maximum limit as 5000 hrs / week then copy the budgeted units to the "labor" and level the resource "labor" and verify the outcome.



I will suggest to give +/-10% to resource levelling for more reflexible simulation



Good Luck



Alex

A
amit parmar 👤 Member for 19 years 3 months

Second: If you need to level your resource to max 5000hrs/week.Then you need to calculate the unit/time according to total 5000hrs/week.Then assign this value in max units/time.Then you can veiw the resource usage profile according to week/month and use the option of showing overloading.The max units will be calculated as 5000hrs (if you have calulated the max units/time correctly) and then you can level the resouce accordingly.

A
amit parmar 👤 Member for 19 years 3 months

You can only assign units as Hrs for labour and non-labour units

If you want to assign separate units for your resource then you need to assign it as material resource.if the particular unit is not shown in the units tab,then you can add a particular unit by going to the option admin>admin categories>units of measure and there you can sepicfy the particular units you want to use.

D
Dieter Wambach 👤 Member for 19 years 5 months

If you need inches, these will be a material resource.

I’m afraid, a limit of 500 hrs a week as a maximum is not possible for levelling.



Regards

Dieter

D
Dieter Wambach 👤 Member for 19 years 5 months

Hi Minhas



P3e knows 3 types of resources:

- labour

- non-labour i.e. machines, equipment,...

- material



Units %-complete is only calculated from labour and non-labour

Regards

Dieter

A
Anoon Iimos 👤 Member for 19 years 8 months

It’s a matter of conversion using productivity rates. You can never have common unit for non-labor, so you have to convert it into hours or cost or whatever you want as long as it is common to all your tasks.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts