MS Project Server - Project Interim variance

S
Stephen Grady 👤 Member for 22 years 10 months

Thanks Brian - that works!



I must remember to select the "use Formula" option in future.





Cheers



Steve

B
Brian Ultican 👤 Member for 19 years

In the customize field dialog there is a section called "Calculation for task and group summary rows". In it select "Use Formula". This will have the variance calculated at the summary task levels within your project, including at the project summary task level.



Remember to use an Enterprise level field if you want this to be calculated for all your projects.