Sve ur baseline project as a newfile using save as option...
Now auto update the project keeping the status date as the project finish date..Once u have updated, all the activities in ur project shows 100% completed...
Now. using the reports, create a chart for the progress completed by months...this will be the monthly / cumm. progress planned for ur project...
export the monthly progress % completed values to an excel sheet and compare this with the actually progress % acheived..
You can create a resource R and then allocate the budgeted quantity for the respective activities equal to original duration and then graph the resource R.
This is helpful during early stages of the project, when you are not sure of the quantum of resources and you wanna have S Curve for monitoring.
But, in the later stages S-Curve must be drawn for resources or cost.
What kind of "S" curve do you want. Specifically, what are you trying to graph against (as a function of) what?
An S curve is usually Cumulative Cost or Cumulative Work (Hours) on a vertical axis against time on the horizontal axis.
It could be Cumulative Duration against Time as well, I guess, but this would not mean very much or be very useful.
MSP will allow you to assign Work without necessarily assigning Resources.
It will also allow you to assign Costs as Fixed Costs against Tasks (Cost Table, Fixed Costs).
Then use the Analysis Toolbar to export the data and graph it in EXCEL.
If you do want to graph Cumulative Days against Time, although I am not sure why this would be useful, you could create a Resource called, say, "One Day" and assign it to every Task, then use the Analysis Toolbar and graph the Cumulative "Work" of that faked Resource.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Riaz,
U can try this..
Sve ur baseline project as a newfile using save as option...
Now auto update the project keeping the status date as the project finish date..Once u have updated, all the activities in ur project shows 100% completed...
Now. using the reports, create a chart for the progress completed by months...this will be the monthly / cumm. progress planned for ur project...
export the monthly progress % completed values to an excel sheet and compare this with the actually progress % acheived..
Venkat
In short,
You can create a resource R and then allocate the budgeted quantity for the respective activities equal to original duration and then graph the resource R.
This is helpful during early stages of the project, when you are not sure of the quantum of resources and you wanna have S Curve for monitoring.
But, in the later stages S-Curve must be drawn for resources or cost.
Cheers,
Raviraj A Bhedase
What kind of "S" curve do you want. Specifically, what are you trying to graph against (as a function of) what?
An S curve is usually Cumulative Cost or Cumulative Work (Hours) on a vertical axis against time on the horizontal axis.
It could be Cumulative Duration against Time as well, I guess, but this would not mean very much or be very useful.
MSP will allow you to assign Work without necessarily assigning Resources.
It will also allow you to assign Costs as Fixed Costs against Tasks (Cost Table, Fixed Costs).
Then use the Analysis Toolbar to export the data and graph it in EXCEL.
If you do want to graph Cumulative Days against Time, although I am not sure why this would be useful, you could create a Resource called, say, "One Day" and assign it to every Task, then use the Analysis Toolbar and graph the Cumulative "Work" of that faked Resource.