Dear Paul,
When you do automatic update, then P3 assume that everything are moving as per plan and update every activity as per initial base plan. If there are any deviations then update as mentioned by Arvin and Anoon.
Regards
some people are claiming that P3 is becoming obsolete while others still dont have a clue! (including me);
P3 is using Duration; Resource Units and Costs
in updating P3 by just putting actuals, make sure you chose Duration
when youre using Resources Units (which i supposed seldom used or never), make sure you got all the quantities!
when using Cost! Im sure youll never get what you want!
Agree with Arvin.. if youre updating your program just put all the actuals and press F9..
Because
Update progress is an automatic way of updating a project. Meaning P3 quickly estimates activity dates, percent complete amounts, and remaining durations as of the new data date you specified by dragging the data-date line or by using the Progress Spotlight feature.