Update Progress P3 3.1

A
Amreshwar Shukla 👤 Member for 23 years 1 month

Dear Paul,

When you do automatic update, then P3 assume that everything are moving as per plan and update every activity as per initial base plan. If there are any deviations then update as mentioned by Arvin and Anoon.

Regards

A
Anoon Iimos 👤 Member for 19 years 8 months

some people are claiming that P3 is becoming obsolete while others still don’t have a clue! (including me);



P3 is using Duration; Resource Units and Costs



in updating P3 by just putting actuals, make sure you chose Duration



when you’re using Resources Units (which i supposed seldom used or never), make sure you got all the quantities!



when using Cost! I’m sure you’ll never get what you want!

A
Arvin Dayday 👤 Member for 19 years

Because



Update progress is an automatic way of updating a project. Meaning P3 quickly estimates activity dates, percent complete amounts, and remaining durations as of the new data date you specified by dragging the data-date line or by using the Progress Spotlight feature.

Forum Sponsor

Top Posters

Syed Shoeb
0 posts
Viet Tran
8 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts