import P3 to P5

F
Frank Neal 👤 Member for 23 years 4 months
F
Frank Neal 👤 Member for 23 years 4 months

All sorted, we had 10hrs / day, as soon as you change to 8hrs /day the odu returned back to its origianl value..



many thks



dinesh.!

S
Sadia Janjua 👤 Member for 19 years

I had the same problem. The solution to this is when you schedule your schedule make sure you select the progress overide. Your dates should match

D
Dinesh Kumar Damavarapu 👤 Member for 24 years 3 months

Hi Frank,



Try the following:



Go to Admin, Admin Preferences and look at the Time Periods tab. Make sure that the Hours/Day setting matches the setting from where the project came from.



In the case of importing from P3 projects, if the planning unit is Days, then set the Time Periods to 8 Hours/Day.





In P3, you are allowed to make the Original duration and Remaining duration different for Not Started activities. When they are imported into Project Management, it will set the Original duration to match the Remaining duration by design.



The P3 user must either update the remaining duration to match the original, or set an actual start on that activity in order for the durations to match what is in P3



Cheers..



Dinesh

F
Frank Neal 👤 Member for 23 years 4 months

many thanks, will take a look tomorrow..



I actualy created a barchart view in P5 ( daily) and couunted the bar periods, = 26 days, which was the original p3 odu, but now in P5 the odu = 21 days! How can the periods = 26 on the barchart, but the odu = 21?

R
Ronald Winter 👤 Member for 23 years 5 months

The answer is "Interruptible Activities." P3 supports this CPM calculation option while P5 does not. You have doubly-constrained activities that were stretching to meet both restraints in P3. In P5, the finish restraint always takes precedence. Good luck!

F
Frank Neal 👤 Member for 23 years 4 months

Not sure, I will re-check and see if that has any impact.



thks



Frank

S
Santosh Bhat 👤 Member for 21 years 2 months

I can’t really think about other things at this moment - but one common problem I’ve encountered is this- did you schedule the project in P3 immediately before importing it? Some problem have been overcome by shceduling in P3, then importing right after the scheduling is completed.


F
Frank Neal 👤 Member for 23 years 4 months

Yes, just checked we are using Release 5.0 SP3 ( 30000050)



Thks for all of your suggestions...keep going...

S
Santosh Bhat 👤 Member for 21 years 2 months

If start and finish dates are the same, yet durations are different - then its a calendar related problem.



1) check what the default calendar for the project now is

2) then manually check that the calendars beign used are in fact the same.



For 2) you can’t print calendars in P5, but i suggest you pick an activity that is showing the duration change, and compare the periods between the start and finish dates across both P5 and P3 calendars for any differences in the number of work days.


S
Santosh Bhat 👤 Member for 21 years 2 months

The task you’re referring to - was it a hammock in P3? and is now a "Level of Effort" activity?

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts