How to Know the total No of activities in a layout ?

I
Ife Olyke 👤 Member for 19 years 4 months

Hi Planners,



When i try to run matrix report for the number of activities in my schedule, i get the error message:



invalid code specified for project code



Can anyone guide me please? Thanks.


K
KongChung Chan 👤 Member for 21 years 10 months



Why not try the matrix report in P3.



tools - > tabular -> matrix -> actvities



Not only you get the number of activities, you can break

that down by category too.

A
Andrew Podolny 👤 Member for 21 years 7 months

Here is my suggestion.



Tools->Tabular Reports->Report Writer->New Report



Content -->Data Item: NACT (Number of Activities)

Total: Yes

Selection--> Your filter criteria



Run Report

That’s it



Cheers Andrew

U
ulysses garcia 👤 Member for 20 years 9 months

Hi Franb,



Just run it to schedule now or find the icon that look like a clock then click it. or just simply run your schedule you will read the result in the report. ihope this will enlighten your question. If you are using primavera p5 you will easily count the no. of activities by adding column to it as it is incorporated in the tools.



uly

P
Pranab Kumar Deb 👤 Member for 19 years 4 months

Hello Hemanth ,

I really canot read that fast, Thanks Frank that was a great information indeed

regards

deb

H
Hemanth Kumar 👤 Member for 23 years 7 months

Sorry



2000 out of 4000



4000 is the total no of activities in that layout

H
Hemanth Kumar 👤 Member for 23 years 7 months

Follow Frank Is Advise

Or If Your Project Is Really Big
When You Open A Layout You Can See something like this

"Organizing Layout 2000 out of 4000 (50%)
obviously 2000 is the current activity count

Run Filter Once More To Make Sure

hemant

F
Frank Borcherdt 👤 Member for 25 years 1 month

3 easy steps:



1. Create an activity custom data item as numeric called activity count

2. Use global change to assign 1 to this field on every activity (or use a column with fill cell)

3. Configure the column in the layouts that you want to this field and remember to group by at least one field (Project if nothing else) with a Total at Top (or bottom).



You now know the count.



HTH

Frank Borcherdt

P
Pranab Kumar Deb 👤 Member for 19 years 4 months

hello ashraf ,

Not every exercise is of same value to all professionals .

anyways thanks for your advice and time.

regards

deb

A
Ashraf Jahangeer 👤 Member for 19 years 1 month

Hi Deb,



I cant think of any right now, anyway let me know what value you will add by counting the number of activities in a layout.



Regards,



Ashraf

P
Pranab Kumar Deb 👤 Member for 19 years 4 months

Hello Ashraf,

without exporting to layout can’t this be counted in the program itself.

regards

deb

Forum Sponsor

Top Posters

sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts