Click Project

Project Information

In the Start Date box, give the new Start date (20 March or whatever).



That’s all. Now your new project will will have a default start date of 20 March.



Good luck.

R
Rodel Marasigan 👤 Member for 19 years 9 months

Hi Mark,



1) Click Print Preview

2) Change all the setting on page setup based on your requirement such as Header, Footer, Margin, Number of Columns..etc..

3) Click Print -> then change the timescale dates from and to (range of date to print)

4) Click Preview to check if everything is Okay.

5) If your happy on the settings Click Print -> Okay.



That should solve your problem.



HTH

Rodel

M
Mark M 👤 Member for 19 years 2 months

I have a slightly different problem with the dates in the Gantt view.



My document is also a copy of an earlier project. I have saved the view so it shows the correct dates, but when I print the Gantt it starts several weeks before the actual start date of my project.



I’ve updated all the dates in the project, and the overall project start date. I have also cleared the baseline information.



Am I missing a simple way of defining the print range of a Gantt chart?



thanks

Mark

R
Rodel Marasigan 👤 Member for 19 years 9 months

Mudar,



Move the view using horizontal scroll bar start to any date you want and save. Every time you open your project your view will start on the save view date.



Rodel

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts