Forecasting methods studies in Earned Value Analysis

E
ersin namli 👤 Member for 20 years 10 months
E
ersin namli 👤 Member for 20 years 10 months

First thanks for your interests. Softwares that we use for Earned value Analysis use basic math and basic formulas for estimation. It’s easy to see current estimtion methods are unreliable and useless. Ofcourse I know what is Eaned Value and what Earned Value is not. I was waiting different ideas but anyway thanks again

I’ll inform you about progress.

O
Oliver Melling 👤 Member for 19 years 1 month

EVM is definately a topic that you could cover in a doctorate thesis.



For instance, the application and suitability of its use in different industries is one area that could be explored, as is the testing of its limitations and possible areas for improvement, such as introducing ’earned schedule’ methodology.



However, the fact that someone is doing a doctorate on EV and doesn’t know about things such as EAC and TCPI is suspect.



’Isnt it still a guess multiplied by a guess ?’



Even quantum physics and the theory of relativity are guesses based upon guesses.

S
Steven Oliver 👤 Member for 23 years 7 months

I find it incredible that someone claiming to be



"studing Earned Value Management in my doctorate thesis ", should be asking such a basic question.



Further, since when did EV become such a science that it necessitates a doctorate thesis?.





Isnt it still a guess multiplied by a guess ?

A
A D 👤 Member for 19 years

On PMI’s website (www.pmi.org) book on earned value analysis is available.



This is one of the best book I have ever read on earned value analysis. But, you need to purchase the same.



It covers basic elements, EVm performance Analysis and Forecasting, gives guidance for use of key EVM practices.



Cheers,



Raviraj A Bhedase

A
Andrew Dick 👤 Member for 19 years 3 months

Here are some others to get you started



I’m quite sure there will be heaps more offered soon





EV Formula

Schedule Variance Dollarised, SV$ = BCWP - BCWS

Schedule Variance Percent, SV% = SV$/BCW S* 100%



Cost Variance Dollarised, CV$ = BCWP – ACWP

Cost Variance Percent, CV% = CV$/BCWP * 100%



Percent Complete, %C = BCWP/BAC * 100



Schedule Performance Index, SPI = BCWP/BCWS

Cost Performance Index, CPI = BCWP/ACWP

To Complete Perf Index, TCPI = (BAC-BCWP) / (EAC-ACWP)



Estimate at Complete EAC = ACWP + ETC

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts