1. MS Project (MSP 2007 included) does not know what a resource bar chart is; therefore the only way to display resources and their task or non-working day allocations would be to use the Using Resource view; this view is a table, not a chart
2. To display resources work and non-work allocations separately, you will have to allocate resources to tasks that represent regular work AND to "tasks" that represent non-work period; obviously you will NOT use resource calendars as well
3. If you insist for viewing the tasks in a bar chart instead of a table, I only know the 2 following ways: a) MS Project Server and project Web Access, that know what a resource bar chart is (but a resource bar chart in PWA is for individual resources, not for entire projects), and this solution is rather expensive; b) ask this friend of mine http://www.stk-management.fr/ about his solution to build a resource gantt chart from the regular task gantt chart of your project.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Damian,
1. MS Project (MSP 2007 included) does not know what a resource bar chart is; therefore the only way to display resources and their task or non-working day allocations would be to use the Using Resource view; this view is a table, not a chart
2. To display resources work and non-work allocations separately, you will have to allocate resources to tasks that represent regular work AND to "tasks" that represent non-work period; obviously you will NOT use resource calendars as well
3. If you insist for viewing the tasks in a bar chart instead of a table, I only know the 2 following ways: a) MS Project Server and project Web Access, that know what a resource bar chart is (but a resource bar chart in PWA is for individual resources, not for entire projects), and this solution is rather expensive; b) ask this friend of mine http://www.stk-management.fr/ about his solution to build a resource gantt chart from the regular task gantt chart of your project.
Hope this helps
Alexandre