Here in Brazil we are not using Suretrack any more. MSP is the most popular planning and control software because it is easier to find professionals with expetise in this software, price, many good curses, books and consulting.



The usage of Primavera 5.0 is increasing quikly.



Regards.

R
Rodel Marasigan 👤 Member for 19 years 8 months

Donovan,



Logically no difference at all. It’s only the environment and some enhancement tool on the software.



Other issues are:

MSP98 can save or export to MPX, MSP2003 is not.

MSP98 calculate relationship base on predecessor, MSP2003 use successor

D
Donovan Scholtz 👤 Member for 19 years 1 month

Thank you. For the link.



Question, is there a big difference between MS project 2003 and 98, and Suretrak Project Manager 2, and version 3.0a?

Forum Sponsor

Top Posters

paulciszewski
0 posts
Catalin Suditu
11 posts
Laraib Fatima
0 posts
Adrian Fletcher
12 posts
GeoVe
0 posts
James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts