Piping Tie In Lead Times

A
Anshad NK 👤 Member for 20 years 1 month

Hay Andrew



If you are looking for the Procurement of Materials, then you should take into account what time it takes for the following...

1.Preparation & finalisation of Material Requisitions,

2.Issue it to Vendors for quotations

3.Technical bid evaluation is to be done

4.Prepare the purchase order ...

Also you ve to consider the lead time required ...



it would be better if you talk with your procurement guy..or directly with the Subcontractor regarding all these....



hope this clears ur doubts...



& for your info I am not a procurement guy...


H
Hernando Pesca 👤 Member for 19 years 1 month

Andrew,



How big are the pipes? This is a prime consideration especially for large diameter. I suggest to get a the schedule of your subcon and check if their time-frame fits your master schedule. If not go back to them and compress.



Hernan

A
Anoon Iimos 👤 Member for 19 years 8 months

i’m afraid i’m not qualified to answer that. please refer to the one incharge of the procurement

A
Andrew Sherwood 👤 Member for 19 years 2 months

The fabrication will take no time...Just to weld a valve onto a piece of CS pipe...I’m more concerned with how long it will take to procure the materials...They are doing the procurement, just wanna make sure I fit it into the schedule properly as to when I should get them the piping tie-in package...

A
Andrew Sherwood 👤 Member for 19 years 2 months

Sorry about that, the piping is Carbon Steel...Very short lead times...What they are fabricating in the field would be a valve onto the T, or a putting a blind on the flange, so they can still run the process unit, then we will come in later on and install the new line to the existing...



So baically how long to procure and fabricate the "tie-in", currently I am allowing 12 weeks...

A
Anoon Iimos 👤 Member for 19 years 8 months

what do you mean by CS valves? consolidated safety relief valves?

A
Andrew Sherwood 👤 Member for 19 years 2 months

The sub is only responsible for the tie-in, not actually connecting up the pipe to the tie-in...They are only basically putting T’s and elbows w/ valves...Then we are coming through after and fitting up the pipes...



My question would be better asked if I said how soon should I get the sub the tie-in package, to allow them to procure the CS valves, T’s, elbows...And have time to field fab them...CS has a pretty short lead time..

A
Anoon Iimos 👤 Member for 19 years 8 months

Andrew Sherwood wrote:"My question is how soon before the actual installation should the tie in package be RAS for the sub (Tie-In package contains the weld procedures, P&ID’s, ISO’s, Photo’s of the Tie in Location, etc...)"



that will depend on the length of your piping and the locations of the tie-ins. I suppose it will go at the same time, if your pipes are ready, so are the tie-ins.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts