It would appear that you come from a conventional scheduling background where the end date of a task is calculated from the Data Date plus the Remaining Duration over the task or resource calendar.
Rodel is correct in his statement, but MSP achieves this by splitting in progress task of applying an Early Start Constrain to unstarted tasks.
Microsoft Project ignores the Status Date during normal recalculation. The end date of a task is calculated from the task Start Date plus the Duration.
Basically, to hold a task “In Place” it must have either a Constraint, an Actual Start or a Predecessor. Removing an Early Start Constraint from a task in and in-progress schedule will send the task to the Start Date as MSP ignores the Status Date under normal scheduling conditions.
There are several tools that you may wish to consider when progressing a schedule such as splitting a task etc, using the Tracking Toolbar, etc, etc, but bear in mind that MPS does not comply with generally accepted Critical Path rules when dealing with an in-progress schedule.
Furthermore it takes me a lot longer to manage an in-progress task schedule in MSP than most other software I have used.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Mark
It would appear that you come from a conventional scheduling background where the end date of a task is calculated from the Data Date plus the Remaining Duration over the task or resource calendar.
Rodel is correct in his statement, but MSP achieves this by splitting in progress task of applying an Early Start Constrain to unstarted tasks.
Microsoft Project ignores the Status Date during normal recalculation. The end date of a task is calculated from the task Start Date plus the Duration.
Basically, to hold a task “In Place” it must have either a Constraint, an Actual Start or a Predecessor. Removing an Early Start Constraint from a task in and in-progress schedule will send the task to the Start Date as MSP ignores the Status Date under normal scheduling conditions.
There are several tools that you may wish to consider when progressing a schedule such as splitting a task etc, using the Tracking Toolbar, etc, etc, but bear in mind that MPS does not comply with generally accepted Critical Path rules when dealing with an in-progress schedule.
Furthermore it takes me a lot longer to manage an in-progress task schedule in MSP than most other software I have used.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
Mark,
Select Tools-> Tracking-> Update Project on your Project Menu.
Tick Reschedule uncompleted work to start after: (Data Date)
Tick Entire Project then click Okay
That should move all your remaining duration or uncompleted task start from data date.
HTH
Rodel