Alexandre Faulx-Briole 👤 Member for 23 years 6 months

Stuart,

I am afraid you can’t! Task name indentation is a part of the MS Project format for summary and subsidiary tasks

You could however export the "WBS Index" field together with the other infos, and then write an Excel macro to use this field to indent the tasks in the Excel sheet

Alexandre