a great puzzle in CPM network can someone help me??

Member for

19 years 10 months

Hi Sherif



Samer has sent me a copy of your puzzle in PDF.



I have no intention of doing your coursework for you but the method of solution is very simple and should take you about 30 minutes.



Set the tasks A B C D etc into a gantt chart using the durations and links as stated.



Set them all to ASAP and reschedule - note the dates.



Fix the chart as a baseline and set the tasks to ALAP and reschedule - note the dates.



You now compare the early dates with the later dates. (NET - NLT - which Samer tells me means Not Earlier Than and Not Later Than)



To my mind the whole excercise is completely pointless and is teaching you bad programming habits.



Best regards



Mike Testro

Member for

15 years 11 months

dear guys,



please if any one has a good experience in CPM networks give to me his email to send the puzzle to him because it’s important for me in master degree....the time is an important factor to me for solving it to submit it as soon as possible



regards sherif

Member for

15 years 11 months

dear mike



i’m glad to speak with you , it’s a tricky puzzle ss & ff relations in each activity STF , FTF ,NLT,NET, ES, EF,LS,LF,OD,SS...,FF... some of these items is missed you have to complete it but STF(start total float) & FTF(finish total float) must be different in values...i don’t know what’s meant by NLT & NET...i sent the puzzle to samer’s email ...i hope that we reach a solution for this....thanks for your interest



sherif saied

Member for

15 years 11 months

dear samer



i sent the puzzle to your email ... if you found a solution it’s a great progress waiting for your reply ...thanks for your interest



sherif saied

Member for

17 years 3 months

Hello Mike,



Indeed. Seems that our new friend has something to share, but doesn’t know the write place to post it.