Scheduling strategy

S
Stephen Devaux 👤 Member for 21 years 2 months

Aidan,



In work I’ve done for Drug Information Association, the cost of delay in bringing an average pharma product to market is estimated at about $32. Per second. About $4.6 million per week. I don’t know how much it is for your particular product (if it’s the next Lipitor, add a couple of zeroes!), but you should find out.



If you input constraining dates, it is crucial to quantify their CLUBs (Cost of Leveling with Unresolved Bottlenecks), i.e., how much these constraints are costing by delaying the CPM critical path and project completion. This may allow you to:



1. Justify decisions that would ameliorate the constraints.

2. Look awfully good by showing how many millions of extra dollars your planning and decision-making is adding to the project profit.



Good luck.

A
Aidan Eagers 👤 Member for 19 years 1 month

I agree, we have a design team who are shooting specs at the procurement guy without much thought for a plan so even if the schedule was built the idealistic way i would end up constraining dates anyway.

A
Anoon Iimos 👤 Member for 19 years 8 months

Aidan,



IMO, there’s no other way but to follow your constrained procurement dates, this is out of your control and you can never nail down the completion dates of each of your WBS if these procurement dates were not defined.

K
Karim Mounir 👤 Member for 20 years 2 months

Aidan,



It’s the normal way to drive the procurement dates back from the finish date but actually during updates and the project’s life cycle these originated dates are always delayed many times in the project.

So i didn’t face this except maybe if we are dealing with a subcontractor scope (eg. elevators).



and btw it’s KARIM not KAMIR.



Regards,

Karim


A
Anoon Iimos 👤 Member for 19 years 8 months

you know the problem with pharma.. projects is the chemistry behind it. So you have to be careful with the WBS as you might label viagra with panadol!

A
Aidan Eagers 👤 Member for 19 years 1 month

Kamir,



In this case the WBS that i am treating as seperate are for a procurement cycle, for the instrumentation (small parts but still essential). I have each WBS linked to a milestone so that we get the instrumentation on time but they are not linked in a perfect consecutive order.



Have you come across many schedules that are drivin forward from constrained procurement dates? I know it is better to drive back from finish date required but our validation strategy has not been nailed down and this makes that difficult.



Aidan

K
Karim Mounir 👤 Member for 20 years 2 months

Hi Aidan,



Yes in some projects u can do this, eg. in a cement project the plant consists of departments which are not related to each other (in civil scope) and each department contains more than 1 building, so u link each building within its department and each department should be linked to the completion milestone independently.



HTH.



Regards,

Karim

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts