Progress recording methods

T
Trevor Rabey 👤 Member for 20 years 6 months

sorry, but you cannot unlink remaining duration and % Complete because:



5 Complete = Actual Duration / Total Duration



and



Total Duration = Actual Duration + Remaining Duration



MSP measures Duration, Cost and Work. You can unlink Cost and Work (hours) from Duration. See options, calculation.

I
Iftikhar Awan P.Eng. 👤 Member for 20 years

Thanks Alexandre, your comment clrifies that %complete and remaining duration CAN be unlinked in MS Project. I would check it out.



Thank you Trevor for your comments. You have rightly stated that whenever %complete is stated, we should identify clearly what it means.

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Iftikhar,

it is also possible to update the project with the actual work of resources; by default, actual work and actual duartion are linked, therefore 50% actual work will mean 50% actual duration on one specific task

to unlink these two data, Tools, Options, Calculation, then the 1st option from the top in the frame "Calculation options for (active project)"

Alexandre

T
Trevor Rabey 👤 Member for 20 years 6 months

Do not type in % Complete

Always use an Actaul Start and Actual Duration,

then re-estimate remaining Duration.

MSP will calculate % Complete for you.

T
Trevor Rabey 👤 Member for 20 years 6 months

You have to be very clear about what "% Complete" means.



In MSP % Complete is simply, and always =

Actual Duration/Total Duration.



So % Complete is about Duration only.



What else could it be?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts