Duration Types

N
Nitin Naik 👤 Member for 21 years 4 months
J
John Murray 👤 Member for 19 years 2 months

Some example uses for the Duration Types…



"Fixed Units/Time" – Use against a Level of Effort eg Project Manager over the duration of the Project.





"Fixed Duration & Units/Time" – Typical Construction activity, remaining duration is forecast then this activity type gives the required units/resources per remaining time period (Projecting remaining required project resources to meet schedule), productivity may also need to be considered.





"Fixed Units" – Use for High Level Schedule (perhaps Owners schedule or EPC study phase, Level 1, 2) to assist in determining the overall duration of a program by manually leveling (shrinking and stretching) activities to meet a perceived / achievable resource limit (base resource data is a high level estimate of resources).





"fixed duration and units" - Typical Shutdown / Turnaround activity, when you want to know what it will take to make sure the work is completed on time, this good for re-assessing resource requirement (resource leveling) when a shutdown is in progress.



Many arguments can be put for and against the above; however they are legitimate uses and would be best discussed with Primavera for your particular industry, also I have not looked, but I am sure many example exist on the Primavera Knowledge Base http://www.primavera.com/customer/index.asp



Best Regards

John

P
Peter Nicol 👤 Member for 19 years 2 months

This might help explain things...



The duration type affects the following 3 items:



"Duration"

"Units/Time"

"Units"



Whichever duration type you select will select which one of these 3 items change first. Each duration means the following:



"Fixed Units/Time" - duration changes first and the "units" change 2nd. ie. if you change the duration of an activity, the units will change accordingly (based upon the units/time already set).



"Fixed Duration & Units/Time" - "units" changes first and then duration changes 2nd.



"Fixed Units" - duration changes first and units/time changes 2nd.



"fixed duration and units" - units/time changes first and units changes 2nd.



hope this makes sense



-Pete

A
Aydin Valiyev 👤 Member for 21 years 2 months

Hi Nitin,



You can compare with P3 autocost rules. If you in P3

1. Link RD to % complete it will give you in P5 duration type

2. Unlink RD to % complete it will give you in P5 physical type



I didn’t reach to Units yet.:)



Cheers,

Aydin

Forum Sponsor

Top Posters

Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts