When updating it is useful to first get to the right View and Table so you can see whats happening, and then follow a consistent procedure every time, like:
Show Tracking Gantt
Show Tracking Table
Show Tracking Toolbar
Set Baseline
Set Status Date
Format the gridlines to show Status Date (a fat red vertical line).
Then type in Actual Start and Actual Finish Dates.
If the Task is not Finished, type in Actual Start Date, and Actual Duration, Then Remaining Duration.
The second and third buttons on the Tracking Toolbar are for:
1 ) when work has been done continuously from Actual Start to Status Date, update to the Status Date, then re-estimate Remaining Duration.
2) When work was discontinued after an initial Start, move the unused portion of the Duration (which is to the left of the Status Date Gridline) to the right of the Status Date, then re-estimate Remaining Duration.
Always review/re-estimate Remaining Duration, even if just to leave it as is.
Always use explicit Actual Start and Finish Dates.
Never type in % Complete (let MSP calculate it for you), except for maybe 0% and 100%.
This procedure is pretty reliable and can be extended for situations where Work (Hours) and/or Cost do not get automatically get updated along with Duration.
no wonder i find msp so unpredictable if we update the project. (as we normally would when using p3) msp is good for initial planning; quick and easy, but once u start to update/progress... all hell break loose!!! aaargh!
that explains why some company who uses msp, prefer to "update" by means of progress line update only... the zig-zag progress line at the status date over the "baseline" schedule.
Be aware that MS Project was originally not designed to do this, and it uses some less elegant tricks to achieve that result.
It puts constraints on not-started activities in order to reschedule work after the status date. This will override any existing earlier constraint dates and create constraints on activities that never had one.
Furthermore, for in-progress activities it uses the resume dates to reschedule the remaining work, and in doing so, it overwrites the resume dates of any suspended activities that lay before the status date.
I suppose they could have put it in the Tools/Options/Calculation dialogue box together with the other switches related to the positioning of the remaining duration relative to the status date but then that would make the software user friendly!!
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
I dont find MSP so "unpredictable".
When updating it is useful to first get to the right View and Table so you can see whats happening, and then follow a consistent procedure every time, like:
Show Tracking Gantt
Show Tracking Table
Show Tracking Toolbar
Set Baseline
Set Status Date
Format the gridlines to show Status Date (a fat red vertical line).
Then type in Actual Start and Actual Finish Dates.
If the Task is not Finished, type in Actual Start Date, and Actual Duration, Then Remaining Duration.
The second and third buttons on the Tracking Toolbar are for:
1 ) when work has been done continuously from Actual Start to Status Date, update to the Status Date, then re-estimate Remaining Duration.
2) When work was discontinued after an initial Start, move the unused portion of the Duration (which is to the left of the Status Date Gridline) to the right of the Status Date, then re-estimate Remaining Duration.
Always review/re-estimate Remaining Duration, even if just to leave it as is.
Always use explicit Actual Start and Finish Dates.
Never type in % Complete (let MSP calculate it for you), except for maybe 0% and 100%.
This procedure is pretty reliable and can be extended for situations where Work (Hours) and/or Cost do not get automatically get updated along with Duration.
thanks neik.
no wonder i find msp so unpredictable if we update the project. (as we normally would when using p3) msp is good for initial planning; quick and easy, but once u start to update/progress... all hell break loose!!! aaargh!
that explains why some company who uses msp, prefer to "update" by means of progress line update only... the zig-zag progress line at the status date over the "baseline" schedule.
Be aware that MS Project was originally not designed to do this, and it uses some less elegant tricks to achieve that result.
It puts constraints on not-started activities in order to reschedule work after the status date. This will override any existing earlier constraint dates and create constraints on activities that never had one.
Furthermore, for in-progress activities it uses the resume dates to reschedule the remaining work, and in doing so, it overwrites the resume dates of any suspended activities that lay before the status date.
Alexandre, Thanks for your comment.
I suppose they could have put it in the Tools/Options/Calculation dialogue box together with the other switches related to the positioning of the remaining duration relative to the status date but then that would make the software user friendly!!
Phil,
this functionality is rather new to MS Project; they missed clear space to put it in a dialog box, and they missed a self explanatory nam for it
Alexandre
Eugene, Thanks for your help, it now works!!
Dont know if MS could have hidden that switch any better. Long live Primavera!!!
Rgds, Phil
hv u execute the function to...
Schedule remaining work to start after status date?
it is found in Tools/Project Tracking...