Resource/Cost Loading in P3 based on LS and LF
Forum Sponsor
Top Posters
pennyu
0 posts
James Williams
74 posts
jaasland
0 posts
Doron El
3 posts
Erim INANC
2 posts
gorilpk
0 posts
Ricky
0 posts
pinoyplanner
1 posts
Siddharth Ranadive
1 posts
Aidar Kurmantayev
0 posts
thanks so much Michael, thats correct, because Ive asked the Primavera System and they answer the same.
Good luck.
Louie
Louie,
I have experienced these problems before in trying to develop late data curves through dumping my data into excel. What I found to work, was to create a copy of my schedule offline (call it LATE or whatever you want), and then run a global change changing all of the early starts to late starts, and all of the early finishes to late finishes. Then simply run your reports as normal (early data is now late data)
Good Luck,
Michael
Salamat kabayan...
kABAYAN,
JUST GO TO THE FF MENU:
TOOL , TABULAR REPORTS, RESOURCE, TABULAR THEN ADD.....
IN THE TIMESCALE SELECT THE OPTION YOU WANT.