No of Days in Summary (in Ver 5.0)
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Thank You, It works,
I Change my Default Calander as Activity Calander.
Thankyou Once again
Hi
these are working days. All summaries use the default calendar, your activities have a different one. If youll display start- and finish-dates, start of your first and end of your last activity should be the same as start and finish of the summary.
Regards
Dieter