Thank you all for sharing your views - Quite helpful stuff from Jame especially!
In MS Project, I have grouped tasks using the group by function however, the groups are in ascending order. I need this to be sorted by start date. Is this possible? Thanks
Now that is useful , most annoying before when summary didnt represent the activities that were in view as a result of a filter.
Many Thanks for that
Cheers
Alastair Morrison
The custom grouping function is extremely useful and I use it all the time, in a whole variety of ways. However, one of the most useful aspects of the group-by function is that you can apply a filter and the resultant value in the "summary-bar" is based on the filtered data. In the conventional MSP layout, the summary-task value doesnt change, even if you apply a filter.
James.
Thanks Rajesh
I have also discovered the customise Fields option allowing me to creat group fields to srt and filter on.
Thanks
Alastair
Dear Alastair,
it can be done like this ...
give the group names to different resources ..
then ... Goto Project tab/ Group by / Customize Group by
p3 look can be achieved from here
Cheers,
Khanna