Start with baseline or detailed...?

H
Hazem Rady 👤 Member for 19 years 4 months
G
Gilbert Rayco 👤 Member for 23 years 3 months

Hi Hazem,



Basically u need to develop ur Work Breakdown Structure (WBS)and it is the primary input in schedule activity definition. At the early stage of the project execution upper level of schedule (level 2 or 3)is more appropriate if u do not have enough data or information i.e BOM,detailed AFC drawings, otherwise u can use the top-down method or decomposition,template from previous similar projects or rolling wave planning technique.


J
James Griffiths 👤 Member for 20 years

Hi Hazem,



Welcome to the world of Planning Planet.



At some point in time, you are going to need the detailed description of each activity anyway - so that is where I prefer to begin. This is where the use of standard template is very useful: it should contain all the normal activities associated with a construction programme. All you need to do is change the durations to suit the conditions.



If however, you are planning something that you have never done before, then you would normally start with the expected "generals", and sub-divide them as you spend more time developing the programme.



HTH



James.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts