I have just run some tests with 2007, 2003, 2002 and 2000 versions.
I have found that by adding 2 tasks of 1 day duration and setting the second task to a 24 hour calendar and connecting the two tasks with a FS +5D that 2007, 2003, 2002 calculate on the successor calendar and 2000 on the project calendar as set in the project overview form.
Rodel, give me a call sometime to discuss, 04 1118 7701.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
After a thorough review on programme and logic comparing MSP2002 and MSP2003 I arrive on a conclusion that the main cause of the different output is because of the relationship calendar lag duration used are different from each other. MSP2002 uses the predecessor’s calendar on lag while MSP2003 use the successor’s calendar.
P3e/ PM5 have an option to select which calendar to be used on lag before re-scheduling.
At present, I dont have files in MSP2003. A colleague of mine from previous collaboration loaded MSP2003 in my laptop and we used to prepare our proposal in MSP and P3, but the final submission was in P3.
So my laptop got corrupted and was re-formatted. There was no partition so all files gone.
I come to know about this differences because I read books MSP2003.
strange behavior, because MSP 2003 was supposed to be only a restyling of MSP 2002
I do have this kind of result (or mistake) with MSP in French, because as of the 2002 release the basic standard calendar the working day is only 7 hour long
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Paul,
I do same exercise of what you did on MSP2002 & MSP2003 and gave me different result as shown below.
MSP 2003 result
Task Name Duration Start Finish Predecessor (Calendar)
Sample 3d Tue 27/02/07 Thu 1/03/07
Act1 1d Tue 27/02/07 Tue 27/02/07 Standard
Act 2 1d Thu 1/03/07 Thu 1/03/07 2FS+5d 24hr
MSP 2002 result
Task Name Duration Start Finish Predecessor (Calendar)
Sample 6d Tue 27/02/07 Tue 7/03/07
Act 1 1d Tue 27/02/07 Mon 27/02/07 Standard
Act 2 1d Mon 6/03/07 Tue 7/03/07 2FS+5d 24hr
It clearly shows that MSP2003 used successors calendar on relationship lag while MSP2002 used predecessor’s calendar.
I try to contact you but unfortunately I did not manage to get through.
Regards,
Rodel
I have just run some tests with 2007, 2003, 2002 and 2000 versions.
I have found that by adding 2 tasks of 1 day duration and setting the second task to a 24 hour calendar and connecting the two tasks with a FS +5D that 2007, 2003, 2002 calculate on the successor calendar and 2000 on the project calendar as set in the project overview form.
Rodel, give me a call sometime to discuss, 04 1118 7701.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
After a thorough review on programme and logic comparing MSP2002 and MSP2003 I arrive on a conclusion that the main cause of the different output is because of the relationship calendar lag duration used are different from each other. MSP2002 uses the predecessor’s calendar on lag while MSP2003 use the successor’s calendar.
P3e/ PM5 have an option to select which calendar to be used on lag before re-scheduling.
Regards,
Rodel
Hi Alex,
At present, I dont have files in MSP2003. A colleague of mine from previous collaboration loaded MSP2003 in my laptop and we used to prepare our proposal in MSP and P3, but the final submission was in P3.
So my laptop got corrupted and was re-formatted. There was no partition so all files gone.
I come to know about this differences because I read books MSP2003.
so i cannot sent you any files.
regards,
Charlie
Rodel and Charleston-JOseph,
strange behavior, because MSP 2003 was supposed to be only a restyling of MSP 2002
I do have this kind of result (or mistake) with MSP in French, because as of the 2002 release the basic standard calendar the working day is only 7 hour long
Could you send your file to [email protected]?
Regards
Rodel,
Do the best you can to acquire same version of MS project as the client.
Otherwise, you have to live with the same problem that repeat and repeat until completion of your project.
This is because it is very clear in MS Project 2003 that the new version is totally different from previous versions.
Cheers
Charlie