niles luo 👤 Member for 20 years 6 months

hi,

I had met this problem a few month ago. At that time, I got a conclusion. If we set the interval=week, P6 system can assure the data are right only under the timescale interval is week. If it is month, the data maybe have some variance. For example,

1, the actual period progress of Jan 1 is 5%

2, the actual period progress of Jan 8 is 8%

3, the actual period progress of Jan 15 is 6%

4, the actual period progress of Jan 22 is 7%

5, the actual period progress of Jan 29 is 8% (include Jan 29, 30,31 and Feb 1,2,3,4)

so, if we display the actual progress under interval=month, the value will be 34%. All the progress of Jan 29 will be summary into Jan. In fact, progress of Feb 1,2,3,4 should be summary into Feb. That is the variance.



Best Regards


R
Rodel Marasigan 👤 Member for 19 years 7 months

Haresh,

When running Tools-> Summarize (All Project, Open Project or Summarize only Project), the date interval settings on admin will be use (weekly or monthly).

For monthly it will be per month working hours while weekly will use Weekly working hours defined.

1 year = 52 weeks (which have overlapping month)

1 year = 12 months (have overlapping week)

If you are using Month on Timescale for summarized project then use monthly otherwise use weekly.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts