Adding activities to a plan which has already saved with a baseline; is a simple contractual question.
Are these activities part of your initial undertaking as per your contract? (I mean, have these activities left out by you. If this is true, YES they should be included in the initial baseline. To do this add these to your baseline, DO NOT save a new baseline for all activities.
Otherwise, they should be considered as changes to the contract and hence they are not part of your contractual obligations (Initial Baseline).
What you can do is save the original baseline, show it graphically by editing you bar styles. Change the sequence accordingly in the start and finish columns, save that as Baseline 1, show that graphically by adding it to your bar styles and do the same for the 3rd scenario.
Maybe that will work, I have not tried it myself yet. See what happens and let us know.
Thanks for trying but honestly it didnt help .May be i phrased my question in wrong way.
What i want to achieve is A) I want to make 3 ( I assume MSP allows 11 ) base line plans for a particular project in Particular sequence and B) Then I want to make 3 baselines for same project but with different sequence of activities.
Is it possible i can view all my six plans together ?
I want to do this as in fabrication activity there are many activities we can do in parallel and in more than one sequence.
You probably need to show the default Start and Finish dates rather than Start2/Finish 2.
The idea of copying the dates is a a reference date only, and I suspect that MSP will not allow you to use the Start2/Finish2 fields to update the task start dates.
i have never used interim plans before , can someone explain me the specifics as to how to go about it.
I copied my baselines plan to Start1 and finsh 1 fields. then i inserted start2 and finish 2 column in sheet view. It was here i got stuck as 1) after entering new date in start 2 column , i automatically didnt get finish 2 date ( depending on task duration) & I didnt notice new bar ( as i was expecting it ) was missing from the view.
i know , i am doing something fundamentally wrong , but would be grateful if someone could explain stepwise procedure for it.
A workround may be to copy the baseline start and finish dates into another of the start/finish fields and rename the fields Baseline 1 Start/Finish (or include the baseline date).
Then the schedule could be rebaselined to include the new tasks, but you always have the original dates to refer back to.
If necessary, you could set up a view which has the Gantt chart area bars formatted with the current dates and the "baseline" being start1/finish1 dates rather than the MSP baseline dates.
The problem that you will encounter is that, when you add new activities, they might affect activities that were previously on the critical path. Strictly speaking, therefore, all previous activities that have been affected by the introduction of the new activities need to be re-baselined. Whether your client will allow this is another matter.
If the new activities are stand-alone, and do not affect any previous activities, then you are quite right to select the new activities and save them with a baseline.
You are perfectly right, you should not re-save the original baseline; instead, save another baseline to reflect the project as being completed with the new tasks.
Be aware that MS project will only compute the variance between Current and Original Baseline.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Good day to you all
Adding activities to a plan which has already saved with a baseline; is a simple contractual question.
Are these activities part of your initial undertaking as per your contract? (I mean, have these activities left out by you. If this is true, YES they should be included in the initial baseline. To do this add these to your baseline, DO NOT save a new baseline for all activities.
Otherwise, they should be considered as changes to the contract and hence they are not part of your contractual obligations (Initial Baseline).
Thanks
I. Leontiou
Hello there
What you can do is save the original baseline, show it graphically by editing you bar styles. Change the sequence accordingly in the start and finish columns, save that as Baseline 1, show that graphically by adding it to your bar styles and do the same for the 3rd scenario.
Maybe that will work, I have not tried it myself yet. See what happens and let us know.
Cheers
Julian
Hi Tony ,
Thanks for trying but honestly it didnt help .May be i phrased my question in wrong way.
What i want to achieve is A) I want to make 3 ( I assume MSP allows 11 ) base line plans for a particular project in Particular sequence and B) Then I want to make 3 baselines for same project but with different sequence of activities.
Is it possible i can view all my six plans together ?
I want to do this as in fabrication activity there are many activities we can do in parallel and in more than one sequence.
Thanks ,
regards.
Hi Vinod,
You probably need to show the default Start and Finish dates rather than Start2/Finish 2.
The idea of copying the dates is a a reference date only, and I suspect that MSP will not allow you to use the Start2/Finish2 fields to update the task start dates.
Hope this helps.
Regards,
Tony
Hi ,
i have never used interim plans before , can someone explain me the specifics as to how to go about it.
I copied my baselines plan to Start1 and finsh 1 fields. then i inserted start2 and finish 2 column in sheet view. It was here i got stuck as 1) after entering new date in start 2 column , i automatically didnt get finish 2 date ( depending on task duration) & I didnt notice new bar ( as i was expecting it ) was missing from the view.
i know , i am doing something fundamentally wrong , but would be grateful if someone could explain stepwise procedure for it.
thanks,
regards,
vinod
Julian,
A workround may be to copy the baseline start and finish dates into another of the start/finish fields and rename the fields Baseline 1 Start/Finish (or include the baseline date).
Then the schedule could be rebaselined to include the new tasks, but you always have the original dates to refer back to.
If necessary, you could set up a view which has the Gantt chart area bars formatted with the current dates and the "baseline" being start1/finish1 dates rather than the MSP baseline dates.
Hope this is clear!!!
Tony
Julian,
The problem that you will encounter is that, when you add new activities, they might affect activities that were previously on the critical path. Strictly speaking, therefore, all previous activities that have been affected by the introduction of the new activities need to be re-baselined. Whether your client will allow this is another matter.
If the new activities are stand-alone, and do not affect any previous activities, then you are quite right to select the new activities and save them with a baseline.
James.
Julian,
with MS Project 2000, you will use the second option, that says something like "provisonnal baseline" (or "temporary"?
it is the same thing as Baseline1 to 10 in MS Project 2002/2003
Thanks very much for reply.
I am working in MS Proj 2000, there is not a facility to save Baseline No.1, No.2 etc. as there is in 2003 version.
I work in a Project Management company, the problem is the plan changes so often it becomes a real pain.
Julian,
You are perfectly right, you should not re-save the original baseline; instead, save another baseline to reflect the project as being completed with the new tasks.
Be aware that MS project will only compute the variance between Current and Original Baseline.
Cheers