Zero Float

M
Mark Chapman 👤 Member for 20 years 1 month

Hi Trevor,



Thanks for answer. I would want MSP to show multiple critical paths. I guess I am just not used to this as for example P3 doesnt do this (I think).



Oh well I just need to ensure all tasks arent dangling.



Cheers,



mark

T
Trevor Rabey 👤 Member for 20 years 7 months

perhaps...If they are dangling at the end of a path with no successor and have zero total slack, you must have the "show multiple critical paths" option turned on in tools, options, calculation.



when this option is on, MSP sets the total slack to zero for all tasks in the dangling path, and displays red because total slack = 0.

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts