a) if you use the wizard on any view, ie when in any view, you change the original formatting of that view. Usually, when you apply (the very few) options in the wizard to the Gantt Chart view, the changes are not severe. Same for using the wizard in/on other views, and you can use the wizard to reverse any of those changes. But the wizard doesnt address anywhere near all of the possible format changes that can be made. Even the Page Setup, with footers etc, is stored as part of the view. It is possible to make lots of severe formatting and page setup changes to the Gantt Chart, or any other view, and you could make it a very ugly mess, or lose some of the original formatting or page setup which was serving some practical purpose. How do you get the original back, other than from a clean Global template?
You make some assumptions about the motivation at MS and the "intended" usage of the global template. Yes, it can be used to make available a standard set of views available for all projects. That standard set of views should consist of the clean originals as well as new, customised ones. There is no reason to even keep the new ones in the global template, and it is neater housekeeping to preserve the global template exactly as original, and keep all forms of customisation in separate templates.
There is no reason why a user defined template must only be used for entire "standard projects", and/or standard scope and WBS.
There is no reason why a user defined template cannot be used to store, and make available, customised formatting and page setups, ie views, as well as customised calendars, tables, fields, reports etc etc.
There good reasons for preserving the global exactly as original.
a) it is very easy to get back to the original setup of MS Project views by using again and again the Gantt Chart Wizard,
b) it is also possible to over-write the views stored in the global.mpt template with "fresh" views
c) the global.mpt template was developped by MS in the early 90s to make views, tables, filters, aso available for any project; a project template is used to store standard projects much more than standard formats.
be careful about over-writing the existing views, tables, reports etc that are in the global template with your modified versions of them. You will have no way to get back to the originals.
It is much neater to copy and re-name your version of the view, say "AAA Gantt Chart With Critical Red" and then get a fresh original Gantt Chart FROM the global template, then push your new view into the global template. Even better, you can store all special views in a template file of your own and leave the global as original.
I am a MS Project (amongst others) certified trainer here in France; should you need/want a (good) training on the subject, Id be happy to cross the Channel for a few days.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
I hope I am not arguing.
suum cuique. to each his own.
The question made me think about why I like it that way, but it is just one opinion.
Trevor,
I will not argue.
What you are saying is exactly what I have been fighting against since the days of MS Project 3.0 and the Global.mpt file.
A good reason for NOT using templates to store formating is the HUGE space a MPP/MPT file takes on the hard disk.
A 100 task MS Project file takes more than 100 Kb, when the same in Sciforma Project Scheduler only needs 4 or 5 Kb
QED
All the best
Alex,
a) if you use the wizard on any view, ie when in any view, you change the original formatting of that view. Usually, when you apply (the very few) options in the wizard to the Gantt Chart view, the changes are not severe. Same for using the wizard in/on other views, and you can use the wizard to reverse any of those changes. But the wizard doesnt address anywhere near all of the possible format changes that can be made. Even the Page Setup, with footers etc, is stored as part of the view. It is possible to make lots of severe formatting and page setup changes to the Gantt Chart, or any other view, and you could make it a very ugly mess, or lose some of the original formatting or page setup which was serving some practical purpose. How do you get the original back, other than from a clean Global template?
You make some assumptions about the motivation at MS and the "intended" usage of the global template. Yes, it can be used to make available a standard set of views available for all projects. That standard set of views should consist of the clean originals as well as new, customised ones. There is no reason to even keep the new ones in the global template, and it is neater housekeeping to preserve the global template exactly as original, and keep all forms of customisation in separate templates.
There is no reason why a user defined template must only be used for entire "standard projects", and/or standard scope and WBS.
There is no reason why a user defined template cannot be used to store, and make available, customised formatting and page setups, ie views, as well as customised calendars, tables, fields, reports etc etc.
There good reasons for preserving the global exactly as original.
Trevor,
I do not agree with your post:
a) it is very easy to get back to the original setup of MS Project views by using again and again the Gantt Chart Wizard,
b) it is also possible to over-write the views stored in the global.mpt template with "fresh" views
c) the global.mpt template was developped by MS in the early 90s to make views, tables, filters, aso available for any project; a project template is used to store standard projects much more than standard formats.
Cheers
Alexandre
Mark,
be careful about over-writing the existing views, tables, reports etc that are in the global template with your modified versions of them. You will have no way to get back to the originals.
It is much neater to copy and re-name your version of the view, say "AAA Gantt Chart With Critical Red" and then get a fresh original Gantt Chart FROM the global template, then push your new view into the global template. Even better, you can store all special views in a template file of your own and leave the global as original.
Mark,
you are welcome!
I am a MS Project (amongst others) certified trainer here in France; should you need/want a (good) training on the subject, Id be happy to cross the Channel for a few days.
Just ask!
All the best
Alexandre
Well done Alexandre. Yes I had seen this before but it was about 18 months ago and this time I couldnt find it. Many thanks.
Mark,
open a project and display the gantt chart; the open the format menu and play the gantt chart wizard to display the critical task bars in red
open Tools, Organize and copy the Gantt chart from your project (right hand column) to the Global.mpt template (left hand column)
thats all, man
Alexandre
You could create two "Views", identical apart from the redness of the critical path, you will then be able to switch between these two "Views".