Actual Financial period Cost disapear after copying a

A
Alex Wong 👤 Member for 23 years 4 months

Filippo



Sereval things you can check,



1. At the resource assignment level the period data in Sept-Oct-Nov still exist.

2. Have you summerised the schedule - if not then you will not see the updated info in tracking view

3. in the resource profile view are you display "All Project" or "Opened Project only"



HTH



alex