How to filter out only those activities driving a task?
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
There is another existing enhancement request to show which relationships are driving, as a column.
I know this is not what youre asking, but in case you dont know, you can show (with a tick) which activities are driving, within the Predecessors or Relationships/Predecessors tabs.
To show driving relationships only in a layout is an existing enhancement request, according to the Primavera Knowledgebase.
Thanks for that Alex.
Its not the simple answer I was hoping for! Ah well, I guess we will have to wait for Primavera to add it as a function.
Trace Logic is the closest we have found to an answer but its still not as good as "Display driving links only" in Pertmaster.
Again, thanks for your time.
David
David
to do that you need the un progress baseline schedule
What I normally do is since some of the activity is already completed and finish so it is very hard to filter and trace all the activity which is linked to this particular activity,
to filter that first step is use the baseline schedule (With the same logic sequence) (make a copy) - add a finish no later constraint in the tail activity with a very very early day 2 year before its early finish day or something like that
Schedule the plan
Filter the activity with excessive negative float,
Remove the constraint
Schedule the plan again
Then you will have all the activity that have assoication (link) with this activity
Sort the activity by total float
the lease float activities are the critical path for that particular activity, and the rest is on the critical path but not necessary as the critical activity
HTH
ALex