Negative Float

A
Alan Muir 👤 Member for 19 years 6 months
B
Brennan Westworth 👤 Member for 23 years 4 months

Late start or finish constraints can also cause negative float when the activity logic and durations push past this date.



Negative float = early dates > late dates

A
Alan Muir 👤 Member for 19 years 6 months

Cheers Neil,



You were right on both counts. I appreciate your time & help with this problem.



Thanks,



Alan

N
Neil Branigan 👤 Member for 19 years 6 months

Dear Alan,



You probably have figured this one out already.



Must finish contraints are the root cause of this in my experience. In particular, at a project level in Primavera (P3e) you may place a project ’must finish by’ contraint. This will impact everything as soon as you start progressing your plan.



Another cause of this is when you have "loose logic". Your plan should input/output logic links except for the 1st and last activity! Loose logic causes havoc with your float calculations. However, it mainly gives you huge float values on certain activities as opposed to -ve float.



Cheers

Neil.

A
Alan Muir 👤 Member for 19 years 6 months

Thanks Charlie,



In my research on other sites/forums today I came across a similar sentiment & am now in the process of reviewing all constraints. This seems to be doing the trick. Thank you for confirming that I’m on the right track. Your help & your time are appreciated.



Alan

Forum Sponsor

Top Posters

Moahmed
0 posts
S Z
4 posts
Iftikhar Awan P.Eng.
19 posts
ahmad rashidi
4 posts
paulciszewski
0 posts
Catalin Suditu
11 posts
Laraib Fatima
0 posts
Adrian Fletcher
12 posts
GeoVe
0 posts
James Williams
74 posts