EARLY AND LATE SCHEDULE
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Dayanidhi,
Your statement “if you are in between early and late dates curve, you are safe” is misguiding. S-curves show the general progress of a project. Just because the general situation is within the norms, does not necessary mean that the critical path is under control. Using late dates to evaluate adequate progress sounds like playing with fire to me.
Best Regards,
THANK U ......
you can use early & late dates to prepare (s-curve), then enter the actual to see where you are, if you are in between early and late dates curve, you are safe. if your actual curve goes below the late dates curve, then you need to take some measures to bring back your project on track.