Just a thought, is the project rescheduling after you make a change? There is a scheduling option called ’Schedule automatically when a change affects dates’. This option is OK for small schedules but with 8000 activities I would have this switched off.



KB

A
Alex Wong 👤 Member for 23 years 4 months

Kevin



Are you using a networked P3e??

Sometime the network traffic is the bottle neck of the slow respond issue.

Talk to your IT helpdesk (Standard reply will be we do not have any issue with our intranet ^&*)

HTH