Project 2007 changes my 2003 durations??
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
MS have added a new resource type cost this appears to give the same affect as my work around. You create the task with a pounds cost in the cost column and duration and then assign the supplier (who you have set as a cost type resource) to the task and it automatically set the works hours to 0 (it even locks you out of the work column). Good Stuff!!!