Progress Monitoring

T
Tariq Usman 👤 Member for 20 years 5 months
T
Tahir Naseem PMP, CCE 👤 Member for 19 years 7 months

Dear Usman

If your project manager insist to change the target pour dates then there will be no affect on your progress monitoring. Because the change in target pour dates will affect your plan progress not actual. Which you calculate from actual pour dates and volume.



What i understand from your question that PM want to change the planning not monitoring.



Regards

Tahir