Using the term "well known" is a matter of opinion. How does it become well known if MS do not inform people ! In NSW, Australia at least, a product with a bug like this classifed as not fit for purpose and normally you would get your maoney back . However we are all involuntary Beta testers in one way or another I suppose
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
My reply is to Paul the moderator
Using the term "well known" is a matter of opinion. How does it become well known if MS do not inform people ! In NSW, Australia at least, a product with a bug like this classifed as not fit for purpose and normally you would get your maoney back . However we are all involuntary Beta testers in one way or another I suppose
Hello,
This problem only occurs with MS Project 2003 Standard 1st release; it does not exist with ANY other version.
Question is: how did THEY not to check and suppress that enormous bug? As Paul said, this is MSP.
Regards
This was a well know problem with early versions of MSP and was fixed with a MSP2003 Hot Fix 832887.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
Tom,
Ive heard of this problem on many occasions. Ive yet to use MSP 2003, so have not encountered it personally.
James.