delay analysis

P
pari alagan 👤 Member for 19 years 7 months
X
X Planner 👤 Member for 23 years 11 months

yes, you have to go back to your contract what does it read on the method of assesment ,



if you are interested in time impact analysis,



u have to use your updated schedule for a certain month and to apply the delays one by one to calculate the impact of these delays, then substntiate your E.O.T claime based on ur approved program.



Regards,

D
Dayanidhi Dhandapany 👤 Member for 23 years 2 months

you have to check with your contract agreement for the method of delay analysis part. Also you can use your approved baseline programme developed in P3 to show the slippage of activities on the critical path and if it is caused by owner’s delay events, then you can claim for EOT as per your contract agreement. (use your current updated schedule in p3 and keep target schedule as the approved baseline programme)



HTH

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts