Sorry but I do not know what BOQ stands for but what may help is by default Primavera projects are setup using Duration as the Percent Complete Type. If you are updating percentages on duration based progress and want the Earned value to be calculated from this percentage then on the Project screen select the Calculations tab and tick "Recalculate Actual Units and Cost when duration % complete changes".
Or try the following might also help
To calculate activity, resource, and expense actuals according to the project plan, rather than hours, units, and completion percentages reported by resources, mark the Auto Compute Actuals checkbox for each resource (in the Details tab of Resource Details) or nonresource cost (in the Expenses tab of Activity Details).
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
angyan
To load the BOQ you can
First set up the CBS activity From the contract items breakdown CBS - Cost Breakdown Strcuture
Then load the CBS activities with the resource unit and cost from your BOQ.
Then breakdown the WBS in accordance with the actual works that need to be preform. (Sometime CBS is not always WBS)
Once this is done, then you update the WBS each month and using the EV from the WBS and update the CBS activities that loaded with the BOQ
Never use auto-complete if you relate your earn vaule with your BOQ
Good Luck
Alex
Thanks,
Please note that BOQ means Bill of Quanitities and in any contract we do have the value of the contract broken down into items of the BOQ.
Regards
angyan
Sorry but I do not know what BOQ stands for but what may help is by default Primavera projects are setup using Duration as the Percent Complete Type. If you are updating percentages on duration based progress and want the Earned value to be calculated from this percentage then on the Project screen select the Calculations tab and tick "Recalculate Actual Units and Cost when duration % complete changes".
Or try the following might also help
To calculate activity, resource, and expense actuals according to the project plan, rather than hours, units, and completion percentages reported by resources, mark the Auto Compute Actuals checkbox for each resource (in the Details tab of Resource Details) or nonresource cost (in the Expenses tab of Activity Details).
Cheers