Gantt Chart

P
Paul Garland 👤 Member for 20 years 5 months

Much of it depends on your settings, however try the following. Create a calendar with 24hr working and make sure the little box work hours/ day has 24 in it.

Assign it to your activity. Your settings may show the duration in days & the admin preferences may be set to an 8 hour day, therefore as you enter 1d, you get 00:00 to 08:00. Unless your administrator can set your default hours per day to 24, you will have to enter the equivalent 8 hour days the show 31-Oct-06 00:00 to 01-Nov-06 00:00 (3d) or enter 24h directly.

Your user preferences can be changed if you want to show the hours worked.

T
Tu Huynh Van 👤 Member for 19 years 10 months

Hi Paul,



Thanks for your infor,

but i mean that:

examp: activity 1 - duration: 1 day (08h), the Bar normaly will be show from 08:00am to 17:00 pm - this is OK, what the solution for this one if we want to show this bar for the whole day: from 00:00am to 24:00



Please advice,



Tu,

P
Paul Garland 👤 Member for 20 years 5 months

I’m not entirely sure what you mean, however if you go to edit > user preferences > and select the Time Units tab, you can set the unit of time to a day rather than by the hour. Also set the decimal places to zero so it will not allow a fraction of a day?

That may do what I think you’re looking for.



Hope that helps



Paul

A
Alex Wong 👤 Member for 23 years 3 months

Dont understand your question please give a bit more info

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts