Primavera 5 graphical reporting tools

I
Ilter Aydin 👤 Member for 19 years 7 months
M
Marcio Sampaio 👤 Member for 20 years 7 months

I use the famous Excel to plot graphs and curves with data coming from P3e.



Regards.

I
Ilter Aydin 👤 Member for 19 years 7 months

thanks for your help i will try to find how it can be done in p5.

A
Alex Wong 👤 Member for 23 years 4 months

Ilter



You can plot traditional S-Curve, stacked histogram in P5 without any third party software. with EV on Hrs or $



Cheers

Alex