Duration calculation by calendar

D
Dave Dodds 👤 Member for 19 years 10 months
M
MK TSE 👤 Member for 24 years 3 months

sorry to let us know, no change in P6. the "duration" is determined by user perference within the "calculated dates" by defined calendar.



Which means the display value in duration is keep on changing if user preference is changed.

D
David Kelly 👤 Member for 21 years 7 months

Version 5 is the same. No "rumors" that version 6 will be any different BUT will probably allow a work-around.

D
Dave Dodds 👤 Member for 19 years 10 months

Dave,

Thanks, I just discussed this with our admin. It does pose a problem to our field plans that do not work 1-8-5. The default for our database has to be 1-8-5 for mfg. Do you know if version 5 has address this?

BTW, 3-1 would have been easy with Utd. It is going to be a tough season as an arab.



Alex,

1-8-5 is 1 shift, 8 hours, 5 days. Therefore 2-10-7 is 2 shifts, 10 hours, 7 days. I don’t know if this is just Canadian terminology, but it makes sense to me.



Cheers and Thanks for the help.



Dave

D
David Kelly 👤 Member for 21 years 7 months

Let me guess.



You changed all the activity’s calandars, but mysteriously all the durations for the summary bars have stayed the same?



In P3e all summary durations are calculated as the number of working periods between the start and finish of the summary bar as measured on the database’s default calandar. The default calandar is "ticked in the global calandar display.

A
Alex Wong 👤 Member for 23 years 4 months

Dave



1 8 5 ??



1:oo - 8:00 5 days??

or

1 Days 8:00 - 5:00

or

1 shift, 8 hrs days and 5 days??



Please clarify



Alex

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts