Progress line question (Bug?)

A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

Believe it or not...

There are plenty of things that you would like MSP to do and that MSP does not..

THIS is not a bug, you might rather call it a non-functionnality".

Send mails to your nearest MS representative to suggest this functionnality be implemented in the next version.

Alexandre

M
Marc Borburgh 👤 Member for 22 years 3 months

Nice answer.



So we can conclude that MSP can schedule in minutes, hours, days, weeks and more, but is not able to show a progress line that’s on the exact Status Date set in the project (ie. Oct 14 16:00) ??



I find this very hard to believe. A planning package that has a minimum planning unit of minutes and can’t even set the progress line on hours. Odd.

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts